The Build

The Boskins

Internal building work started in January 2018 while we were waiting for Planning Permission to come through.  This involved some serious excavating of the floors in order to install underfloor heating.  Prior to any excavating it was essential to remove as much of the internal structures as possible so that we could reinstate them into the fabric of the renovation – inspiring the name of the building.

It was always important to us to maintain as much of the existing character of the building, which meant we have left the original ceiling of wooden beams in most of the rooms and exposed stone walls.  These were all sand blasted to remove years of paint and grime and restore them to their original colours.

A major piece of work involved replacing all the external doors and windows – replacing white plastic UPVC with traditional wood and a solid stable door as the entrance.

Step By Step

The original state of the walls

History preserved

DSC00384

Plumbing goes in

Stripping back to stone

DSC00478

Underfloor heating installed

 

Walls and beams sandblasted

DSC00482

Wall are now prepared with waterproofing

DSC00496

Boskins are reinstalled to form part of the walls

Electric wires installed ready to be connected

Plastering begins

New windows and door fitted

Doors and windows painted

DSC00826

First coat of paint on the walls

DSC00833

First stage of the kitchen complete

DSC00828

And now with wall and floor tiles

DSC00857

And the bathrooms have tiles too

The lounge floor goes down…looking good

DSC00899

Bathrooms almost complete

And now the work starts on the outside

DSC00931

The outside area is really taking shape

The bedrooms are complete

And complete with handmade doors

 

Speight Cottage

From the first moment we saw this little cottage we always imagined it would make a wonderful place to stay with its fabulous view over the fields and river, but we also realised it would take a fair amount of work.

Originally, it consisted of 3 individual rooms so new doorways needed to be made to form the bedroom and bathroom.  It also needed a new window opening and the entrance moving to the river side of the building.  The roof also needed to be removed, insulated and then replaced as well as excavation of the floor to install underfloor heating.  Again the plastic windows have been replaced with lovely wooden ones.

Step by Step

The original fireplace

DSC00398

But underneath….

First new doorway

DSC00400

Walls prepared

DSC00519

Underfloor heating installed

DSC00522

Fireplace restored ready for wood burning stove

DSC00610

From this…

DSC00612

To this…..

DSC00623

to the new windows and door fitted.

DSC00791

Throw in a little snow to make the builder’s life easier

DSC00634

The view from the new bedroom and bathroom windows

The outside is taking shape…new windows and doors in place and with a coat of paint

DSC00838

Walls and ceilings plastered

DSC00842

Construction is still taking shape but its beginning to look like the finished product

DSC00843

Just need a patio to install this

eclipse 2

The patio is starting to take shape and we now have steps into the cottage

The kitchen goes in

DSC00933

The shower room is started

DSC00936

Painting and pointing complete

DSC00942

And the outside is starting to look good

DSC00924

Ready for the hot tub

DSC00968

And it has arrived

DSC00991